1.
What happens to planned after it has been converted
into production order?
Answer : When
you convert Planned order
to Production order. the planned order are offset
by production order. Reference of planned order can be seen in the production
order.
2.
How to attach a drawing for a material to BOM? Is it
possible?
Answer : Yes,
you can attach a drawing.
First create a document using Transaction Code "CV01N - Create Document".
Attach your drawing in that document.
The system will generate a document number. Assign this document in the BOM with item category D.
First create a document using Transaction Code "CV01N - Create Document".
Attach your drawing in that document.
The system will generate a document number. Assign this document in the BOM with item category D.
3.
What is the output of MPS run?
Answer : From
MPS run you plan the materials which are of 'A' type in the abc analysis (80%
dollar value) that have to be planned before hand.
MPS is also a type of MRP only in which components just below the materials on which MPS run is taken place, are planned.
MPS is also a type of MRP only in which components just below the materials on which MPS run is taken place, are planned.
4.
How to delete groups of products?
Answer : Delete
the members in the product group and then archive the product group in
transaction SARA, object=MM_MATNR.
(The product group is created as a material master record with material type PROD and this record is deleted in SARA.)
(The product group is created as a material master record with material type PROD and this record is deleted in SARA.)
5.
How you define Standard Cost and Variable cost in PP?
Answer : Standard
cost is the cost which is fixed for a period, variable cost is varying with period. As for example
cost of semi finished, finished materials are fixed & cost of raw materials
are varied
6.
Where can you find Read PP Master in SAP(PP)?
Answer : You
will find in master data tab
page of production header data overview, CO02 - Read PP Master Data. Also from
Functions menu you will get Read PP Master Data. This means that you want
the system to re-update the production order with the latest BOM structure.
7.
What are all the settings done for configuring integration of PP with
FICO?
Answer : Assigning of
Cost center to work center.
Assigning Activity type to work center, Standard Cost estimate, Costing Run,
Order settlement, Product costing.
8.
Can MRP be carried out for one particular level of a
bom ( Level code : 0001/0002 etc)?
Answer : Yes it can be done by running for specific materials
(Single Material Single Level)
9.
How Requiements( PIR,Sles Order, Customer
Requirement) are reduced after they are produced?
Answer : Requiements are reduced
automatically after Delivery is made to the Particular Order
10.
Can't one material be assigned to more than one
operation in a routing?
Answer : One material from a BOM CANNOT be assigned to different Operations.
It can be done by defining the material for so many times as required in the BOM
It can be done by defining the material for so many times as required in the BOM
11.
How to insert an inspection checkpoint at the end of
an operation?
Answers : If in process
sample is to be defined, assign inspection type 03 in the
Material Master. Then create MICs and assign
them in the Routings. System automatically generates the Inspection Lots
12.
Where we have to specify the teardown time in one
operation?
Answer : Teardown time can be defined
as one of the Standard Parameters...
13.
How the process time is calculated in a WC when both
labour, Machine categories exist?
Answer : Scheduling is done based on the Capacity Category we define
in the Workcenter
14.
How to create opbject dependencies in a BOM FOR A
CONFIGURABLE MATERIAL?
Answer : Go to Extras -> Object Dependency -> Assign
For this U need to create Characteristics and Class (of Class Type 300) earlier
For this U need to create Characteristics and Class (of Class Type 300) earlier
15.
Can any body explain me why work scheduling view is
required for semi finished and finished products?
Answer : Because we'll mention all details
in MRP views, We need to maintain working
scheduling view in order to make that finished or semi finished
goods available for production as we assign production scheduler and production
scheduler profile in this view, if not maintained conversion of planned order to production will not be
possible.
16.
What is
pre-sales activities can do?
Answer : pre-sales activities can be
inquiries or quotations entered in the system
17.
Mentions 3 basic functions of sales order
system?
Answer :
·
Checking for availability
·
Scheduling delivery
·
Calculating pricing and taxes
18.
Can the resulting data be displayed?
Answer : yes it can be displayed by a user
and in some cases during subsequent processing manually changed by the user
19.
Describe the process in shipping delivery?
Answer : taking into account general
business agreements with your customer à
recording special material requests à
defining shipping conditions in the sales order
20.
What is the purchase order?
Answer : a purchase order is a formal request
to a vendor to supply certain goods or services under the stated conditions
Tidak ada komentar:
Posting Komentar